Client Removes Transmission Lines with Minimal Disruption to Auto, Train Traffic Below | Black & Veatch
Projects

Up in the Air, a Creative Way to Replace Aging Infrastructure

Client Removes Transmission Lines with Minimal Disruption to Auto, Train Traffic Below

Project Name
Housatonic River Crossing Project
Location
Milford, Connecticut - U.S.A.
Client
The United Illuminating Company

Aging infrastructure is a critical issue for the power industry, as utilities work to fill our modern demand for power on equipment built more than a century ago. The United Illuminating Company (UI) ran into this issue near New Haven, Connecticut, when it faced the daunting task of replacing existing transmission line conductors that were located on 100-year-old lattice towers that had been built on a historic railroad bridge.

The towers carry transmission lines that are part of the state power grid, which consists of hundreds of miles of high-voltage transmission lines that run across New England. The towers had been constructed in the early 1900s atop the Housatonic River Railroad Bridge (aka the Devon Bridge), a historic bridge that carries the Metro-North Railroad’s (MNR) New Haven commuter rail line over the lower Housatonic River.

“UI was facing a two-fold challenge,” said Black & Veatch Program Manager John Rector. “The utility would need to not only build new transmission towers and string new transmission lines north of the existing railroad bridge, but safely remove the old transmission conductors from the existing structures.”

UI turned to Black & Veatch for help, hiring the company as full EPC contractor.

 

The project had many challenges. The conductors rose at a height of 200 feet over the river’s surface. The towers where the conductors were located were initially unsafe to climb. To remedy this, CTDOT replaced the existing ladders and added steel members at key locations to strengthen the towers.

Plus, the bridge is located 30 feet from the Moses Wheeler Bridge, a heavily trafficked, six-lane bridge that carries I-95 traffic over the Housatonic River. Due to this proximity, public safety was a major concern. The project team had to erect (and then remove) a safe work zone across the bridge and completely restripe the highway to make room for the work zone. CTDOT and MNR restricted work hours and work had to stop every 20 minutes while trains crossed the bridge below the workers.

 

By Air or By Sea – Choosing the Right Solution

To remove the conductors, Black & Veatch worked with UI to consider several options:

  • Using a floating barge crane. This option was ruled out due to the limited space between the tower and the Moses Wheeler Bridge (I-95) for the South Circuit, and it was deemed an ineffective option for the North Circuit.
  • Using a helicopter to remove both circuits. This would work for the North Circuit, but CTDOT said it would not be a viable option for the South Circuit.

After careful consideration, it was decided to use a helicopter to remove the conductors on the North Circuit and place a large man lift on the Moses Wheeler Bridge to remove the conductors on the South Circuit.

Approaching the North Circuit removals via helicopter required painstaking coordination with MNR, CTDOT and the Federal Aviation Administration (FAA) to ensure the safety of the vehicles on I-95, the passengers on the MNR railroad, and the general public as the helicopter flew to and from the bridge. After establishing a landing zone on the riverbank, the helicopter was used to fly craft labor and materials to and from the towers. The workers prepped the conductors for removal and removed support hardware and insulators from the towers.  

To approach the South Circuit removals via bridge-based crane, Black & Veatch worked closely with CTDOT, which was responsible for traffic control measures and the FAA for emergency landing requirements. A crane was set up on the bridge to raise personnel and equipment to each of the three towers. The air flow spoilers were removed, and the conductor was prepped for removal. The helicopter removed the conductor using a technique called a reverse rope pull. Lastly, the rope was removed by putting slack back into the spans and pulling the rope over to the bridge deck.

“All the work – both on the north and south circuits – was performed in 20-minute segments to minimize disruption to both the I-95 and railroad traffic, and to ensure the safety of those passengers,” Rector said. “Due to multiple safety factors – including the height and location of the towers and the use of a helicopter – work could only be performed during daylight hours. When inclement weather restricted the use of the helicopter on the North Circuit, craft workers had to climb the towers.”

Black & Veatch also handled the construction of the 14 new transmission structures, which were built on the riverbanks just north of the railroad bridge. The two monopoles that carry 1,200 feet of new high-tension wire at a height of 94 feet over the Housatonic River were each 180-feet tall, supported on 10-foot diameter piers. The tower construction was performed primarily from the land, although a boat was used to carry the wire across the river.

“We put a lot of creative thought and energy into finding the right solution for this project, but that’s our specialty. Black & Veatch delivers the design and planning expertise to help clients be successful,” Rector said.

Meet Black & Veatch

We seek partners in innovation. Let's start the conversation.